Working principle and common faults of screw refrigeration unit

July 4, 2025

Water cooled screw unit is an efficient refrigeration equipment with screw compressor as the core, widely used in central air conditioning systems and industrial refrigeration fields. Its working principle is based on the vapor compression refrigeration cycle, which achieves heat transfer through four core processes (compression, condensation, throttling, evaporation). The following is a detailed analysis

 

1、 Core working principle: vapor compression refrigeration cycle

The water-cooled screw unit achieves heat transfer through the phase change of refrigerant (liquid to gas conversion), and the specific process is as follows:
Compression process: Low temperature and low-pressure refrigerant gas is drawn into the cylinder of the screw compressor from the evaporator. The compressor compresses gas into high-temperature and high-pressure refrigerant gas through the mechanical work of the screw rotor, while the temperature significantly increases.

最新の会社ニュース Working principle and common faults of screw refrigeration unit  0最新の会社ニュース Working principle and common faults of screw refrigeration unit  1

Condensation process: High temperature and high pressure gas enters the condenser (shell and tube heat exchanger) and exchanges heat with cooling water. Heat is transferred from the refrigerant to the cooling water, and the gas condenses into high-pressure liquid. After the cooling water heats up, it returns to the cooling tower for heat dissipation.
Throttling process: The high-pressure liquid is throttled and depressurized by a thermal expansion valve, becoming a low-pressure low-temperature liquid, while some of the liquid vaporizes to form a gas-liquid mixture.
Evaporation process: Low pressure and low-temperature liquid enters the evaporator (shell and tube heat exchanger), absorbs heat from the chilled water and vaporizes, cooling the chilled water to the set temperature (such as 7-12 ℃). The vaporized refrigerant gas is sucked back into the compressor to complete the cycle.

Shanghai KUB Refrigeration Equipment Co., Ltd.

 

 

Free Call Video Chat

 

 

 

Address : No. 328 on the 4th plant hengyong Road, Jiading District, Shanghai
Factory Address : No. 328 on the 4th plant hengyong Road, Jiading District, Shanghai
Work Time : 8:30-17:30(Beijing time)
Phone :

86-021 -63184860-17(Work Time)

86--13916495206(Nonworking time)

Fax : 86-021-53750132
Email : lucy@shkubao.com

 

 
Customer Manager
Mr mick Cai
Phone : +86 13588563336
WhatsApp : +86 13588563336
Skype : kub.mick
WeChat : CP9301
Email : kub02@shkubao.com

 

Miss. Mophy Mao
Phone : +86 15001938306
WhatsApp : +86 15001938306
WeChat : kub-maomao
Email : kub@shhkubao.cn